            CATEGORY                         PROJECT TITLE                        ACTIVITY*     2020-21 AMOUNT

                  1       Citywide Infrastructure Improvements                        C             $     1,000,000

            Funding is provided to address health and safety-related infrastructure issues on a citywide basis. Projects include
            safety and security repairs, air-conditioning, water supply systems, fixtures, and other critical maintenance items.

                  1       Civic Center Parking Structural Repairs                  PP/D/C           $        440,000

            Funding is provided to complete necessary structural upgrades to the parking structure under City Hall East and
            the LA Mall in conjunction with other renovation projects underway within the Civic Center.

                  1       Fire Station 4 - Facade Improvements                        C             $        785,000

            Funding is provided to remediate safety hazards resulting from falling exterior tiles at Fire Station No. 4 and the
            Emergency Operations Center.

                  1       Fire Station Extractor Installations                        C             $        250,000

            Funding is provided for improvements to five fire stations to allow for the installation of fire extractors to sanitize
            turnout equipment.

                  1       New 7th Street Body Shop (Phase II)                         C             $     2,800,000

            Funding is provided for the second phase of a two-phase project for the construction of a new body shop building
            to replace the existing facility located at 2310 East Seventh Street, due to significant structural deficiencies

                1, 3      Operations Valley Bureau Facility Package                   C             $     2,250,000

            Funding is provided to continue improvements at Old Fire Station 39, which will provide a permanent Operations
            Valley Bureau location. Improvements include completion of the second floor kitchenette and sleeping quarters,
            inclusion of an elevator, the development of community amenities on the first floor, and structural seismic upgrades.

                  1       Public Safety Facilities - Animal Services                  C             $        400,000

            Funding is provided to support ongoing capital improvements at various Animal Services facilities.

                  1       Public Safety Facilities - Fire                             C             $        480,000

            Funding is provided to support ongoing capital improvements at various Fire Department facilities.

                  1       Public Safety Facilities - Police                           C             $        655,000

            Funding is provided to support ongoing capital improvements at various Police Department facilities.

                  1       Public Safety Facilities - Police Administration Building   C             $        280,000

            Funding is provided to support ongoing capital improvements at the Public Administration Building.

                  3       Rancho Cienega Sports Complex                               C             $     9,250,000

            Funding is provided to fully offset the Phase I construction shortfall for design  and  construction of a new
            replacement sports facility that includes a gymnasium, fitness annex, bathhouse, and indoor pool.



            * “PP” indicates preliminary study. “D” indicates design. “C” indicates construction work. “R/W” indicates land or building acquisition.