Page 238 - FY 2021-22 Proposed Budget
P. 238

CAPITAL AND TECHNOLOGY IMPROVEMENT EXPENDITURE PROGRAM
                                                      CLEAN WATER SYSTEM

                                         SEWER CONSTRUCTION AND MAINTENANCE FUND
               CLEAN WATER SYSTEM MAJOR PROJECTS                              2021-22 BUDGET APPROPRIATIONS


               COLLECTION SYSTEMS (CS)    [1] .........................................................................................................   $90,931,000
                     74TH STREET SEWER REHABILITATION UNIT 1 - VAN NESS AVE TO WESTERN AVE   $2,588,000
                     CBD SEWER REHAB UNIT 13 - WALL ST TO MAPLE AVE - PILOT                    $348,000
                     COCHRAN ADAMS RELIEF SEWER                                              $1,933,000
                     EMERGENCY SEWER REPLACEMENT                                            $30,000,000
                     ENTERPRISE STREET SIPHON MODIFICATION                                     $111,000
                     MAINTENANCE HOLE RESETTING                                              $1,235,000
                     MAINTENANCE YARD - NORTH HOLLYWOOD FACILITY                             $4,565,000
                     NOS REHABILITATION UNIT 4 TRINITY ST FROM 41ST PL TO ALLEY S/O 23RD ST   $3,181,000
                     NOS REHABILITATION UNIT 8 6TH ST TO 8TH ST RIGHT OF WAY                   $277,000
                     NOS REHABILITATION UNIT 9 ALISO STREET TO 6TH STREET                    $2,115,000
                     NOS REHABILITATION UNIT 10 101 FREEWAY TO CARDINAL STREET               $7,709,000
                     NOS REHABILITATION UNIT 13 FORNEY TO DUVAL                                $576,000
                     NOS REHABILITATION UNIT 14 MARSH STREET TO FORNEY STREET                $9,561,000
                     NOS REHABILITATION UNIT 30 COLFAX TO WHITSETT                           $2,224,000
                     NOS REHABILITATION UNIT 35 NOBLE TO CEDROS                              $3,390,000
                     ODOR CONTROL BALLONA CARBON SCRUBBER FACILITY UPGRADE                   $1,580,000
                     ODOR CONTROL DACOTAH CARBON SCRUBBER FACILITY UPGRADE                   $1,246,000
                     ODOR CONTROL HUMBOLDT CARBON SCRUBBER FACILITY UPGRADE                  $2,393,000
                     ODOR CONTROL NOTF CARBON SCRUBBER FACILITY UPGRADE                        $146,000
                     ODOR CONTROL RADFORD CARBON SCRUBBER FACILITY UPGRADE                   $1,818,000
                     ODOR CONTROL RICHMOND CARBON SCRUBBER FACILITY UPGRADE                  $2,456,000
                     SECONDARY SEWER RENEWAL PROGRAM D CONDITION 01 (P02)                    $1,184,000
                     SECONDARY SEWER RENEWAL PROGRAM - DAR 05 HOLLYWOOD                      $1,474,000
                     SECONDARY SEWER RENEWAL PROGRAM - DAR 06 NORTHEAST LOS ANGELES          $5,228,000
                     SECONDARY SEWER RENEWAL PROGRAM - N04 WASHINGTON BL & SOTO ST           $1,662,000
                     TUJUNGA CANYON AND MARCUS AVENUE SEWER PROJECT                            $308,000
                     WILSHIRE AREA SYSTEM SEWER REHABILITATION                               $1,623,000

               DONALD C. TILLMAN WATER RECLAMATION PLANT (DCT)    [1] ...............................................   $32,798,000
                     DCT ADMIN BUILDING LUNCH AND LOCKER ROOM RENOVATION                       $421,000
                     DCT ADMINISTRATION BUILDING HVAC REPLACEMENT                            $1,046,000
                     DCT ADMINISTRATION BUILDING IMPROVEMENTS                                $1,177,000
                     DCT ADVANCED WATER PURIFICATION FACILITY PRIMARY EQUALIZATION BASIN    $13,887,000
                     DCT ADVANCED WATER PURIFICATION FAC JAPANESE GARDEN LAKE EFFLUENT BYPASS   $555,000
                     DCT AVORS & EVIS GATES REPLACEMENT                                      $3,132,000
                     DCT BERM IMPROVEMENTS                                                   $4,928,000
                     DCT CAPITAL EQUIPMENT REPLACEMENT PROGRAM (CERP)                          $60,000
                     DCT EMERGENCY BACKUP POWER                                              $3,748,000
                     DCT INFLUENT AND EFFLUENT FLOW MONITORING INFRASTRUCTURE                $1,176,000
                     DCT JAPANESE GARDEN AMERICAN DISABILITY ACT COMPLIANCE                    $592,000
                     DCT NORTHEAST GUARD BOOTH RELOCATION                                      $148,000
                     DCT SCREW PUMP INLET GATE REHABILITATION                                $1,675,000
                     DCT UNDERGROUND HPE & LPE VALVE REPLACEMENT                               $253,000

               HYPERION WATER RECLAMATION PLNT (HWRP)    [1] .................................................................   $67,287,000
                     HWRP 1-MILE CHAMBER PUMP STATION                                          $496,000
                     HWRP ADVANCED WATER PURIFICATION FACILITY - LOS ANGELES WORLD AIRPORT   $25,557,000
                     HWRP AWPF MEMBRANE BIOREACTORS PILOT                                    $1,694,000
                     HWRP BIOSOLIDS TRUCK LOADING FACILITY FAN AND DUCTING INSTALLATION        $868,000
                     HWRP BIOSOLIDS TRUCK LOADING FACILITY FAN AND DUCTING PROCUREMENT         $379,000
                     HWRP CAPITAL EQUIPMENT REPLACEMENT PROGRAM                              $6,015,000
                     HWRP CAPITAL UTILITY REPLACEMENT PROGRAM                                  $650,000
                     HWRP CENTRAL STORM DRAIN REROUTING                                        $148,000
                     HWRP CO-DIGESTION IMPLEMENTATION IMPROVEMENTS                           $2,681,000
                     HWRP COLD BOX TURBOEXPANDER CONTROL SYSTEM REPLACEMENT                    $690,000
                     HWRP CRYOGENIC FACILITY COLD BOX 1 & 2 IMPROVEMENTS                       $648,000
                     HWRP DIGESTER BATTERY E IMPROVEMENTS                                    $3,058,000
                     HWRP DIGESTER GAS COMPRESSOR FACILITY OPTIMIZATION                        $122,000
                     HWRP DILUTE POLYMER SYSTEM IMPROVEMENT                                  $2,316,000
                     HWRP FERRIC CHLORIDE FACILITY REPLACEMENT                               $1,797,000
                     HWRP GAS MIXING SYSTEM DEMONSTRATION                                      $273,000
                     HWRP HARRINGTON BUILDING AIR QUALITY IMPROVEMENTS                         $164,000
                     HWRP HEADWORKS FIRE SPRINKLER REHABILITATION                            $1,341,000
                     HWRP HEADWORKS GRIT CLASSIFIER UPGRADE                                    $675,000

                                                             213