GENERAL FUND (cont.)
CATEGORY PROJECT TITLE ACTIVITY* 2021-22 AMOUNT
1, 2, 3 Underground Fuel Storage Tank Repairs and PP/D/C $ 500,000
Replacements
Funding is provided for removal, replacement, and/or abandonment in place of failing underground fuel storage
tanks and associated piping systems.
1, 3 Van Nuys City Hall and Marvin Braude Constituent C $ 352,000
Center Security
Funding is provided for security upgrades at the Van Nuys City Hall and Marvin Braude Constituent Center.
1 Verdugo Hills Pool and Bathhouse C $ 182,000
Funding is provided to proceed with major upgrades to the pool and bathhouse that has been on hold due to an
unresolved shortfall that will be offset through leveraging of multiple program funding sources.
2, 4 Vision Theatre Equipment D/C $ 1,300,000
Funding is provided to purchase and install theater equipment that is needed to operate both the theatre component
and Junior Arts program that is co-located at this facility, in support of art development and job training skills for
local South L.A. residents.
1, 2 Workplace Safety Facility Improvements PP/D/C $ 2,000,000
Funding is provided for workplace safety facility improvements and modifications, including needed plexiglass
installations at City facilities to ensure safe operation and to provide safe work conditions for staff.
1, 3 Yards and Shops - Capital Equipment C $ 500,000
Funding is provided for as-needed repair and replacement of various capital equipment required for the operation
of maintenance yards and shops facilities in order to achieve more efficient operations and associated costs
savings.
3, 4 Yards and Shops Facilities - Needs Assessment PP $ 2,000,000
Funding is provided to initiate an assessment of the overall condition and redevelopment needs for the City’s system
of yards and shops facilities through a phased regional approach. There are 133 yards and shops facilities citywide
that are operated by eight City Departments to support critical service deployments, including first responder
activities. The initial phase will be focused on areas of the Civic Center that support citywide service delivery, and
the South L.A. region in support of social equity objectives. Subject to sufficient funding based on final bid results,
disadvantaged communities within the Valley region would be given priority as part of this initial phase.
Subtotal General Fund $ 27,999,859
* “PP” indicates preliminary study. “D” indicates design. “C” indicates construction work. “R/W” indicates land or building acquisition.