Page 436 - FY 2022-23 Proposed Budget
P. 436

POWER REVENUE FUND

                                                 CAPITAL IMPROVEMENT PROGRAM
                                                                                                   Projected
                                                                                                  Expenditures
                                                                                                    2022-23

                  POWER SYSTEM RELIABILITY PROGRAM
                     PSRP - Distribution...............................................................................................................................................  $                 306,381,000
                     PSRP - Substation................................................................................................................................................                     129,777,000
                     PSRP - Transmission............................................................................................................................................                       40,654,000
                     Information Application System Capital - PSIAT...................................................................................................                       39,689,000
                     PSRP - Generation................................................................................................................................................                       21,340,000
                     Generation Modernization.....................................................................................................................................                            863,000
                             Total...................................................................................................................................................  $                 538,704,000
                  INFRASTRUCTURE
                     New Business - Revenue Generation...................................................................................................................  $                 193,147,000
                     Inter-Agency and Customer Initiative....................................................................................................................                       72,043,000
                     General Facility Improvements - PCM..................................................................................................................                       31,335,000
                     Haynes Generating Station Additions and Betterments........................................................................................                       26,933,000
                     Valley Generating Station Additions and Betterments..........................................................................................                       23,727,000
                     Automatic Meter Reading......................................................................................................................................                       22,948,000
                     Scattergood Generating Station Additions and Betterments.................................................................................                       15,266,000
                     Substation Reliability Improvement.......................................................................................................................                       12,551,000
                     Palo Verde Generating Station Capital Improvements.........................................................................................                       12,094,000
                     Castaic Power Plant Additions and Betterments...................................................................................................                         7,819,000
                     Streetlight Systems...............................................................................................................................................                         6,658,000
                     NERC Critical Infrastructure Protection (CIP) Cybersecurity Power (Capital)......................................................                         6,299,000
                     Generation Station and Power Plant Additions and Betterments..........................................................................                         4,757,000
                     Sylmar Converter Station Additions and Betterments...........................................................................................                         3,416,000
                     Power System General (Capital)...........................................................................................................................                         3,155,000
                     Power & External Energy Resources General Capital..........................................................................................                         2,774,000
                     Critical Infrastructure Protection (CIP) Program Support......................................................................................                         2,229,000
                     General Facility Improvement Transmission.........................................................................................................                         1,804,000
                     PCM General Business Equipment.......................................................................................................................                         1,735,000
                     General Facility Improvement ..............................................................................................................................                         1,733,000
                     Harbor Generating Station Additions and Betterments.........................................................................................                         1,522,000
                     SmartGrid, Infrastructure.......................................................................................................................................                         1,086,000
                     Eastern Stations Additions and Betterments.........................................................................................................                            878,000
                     Generation Miscellaneous Improvements on Various DWP Facilities..................................................................                            559,000
                     Owens Valley Eastern Sierra (OVES) Distribution Additions and Betterments....................................................                            513,000
                     Electrical Transportation.......................................................................................................................................                            120,000
                     Capital Facility Improvements Power System.......................................................................................................                              88,000
                     Transmission Lines Additions and Betterments....................................................................................................                              48,000
                     Power System Disaster Recovery (Capital)..........................................................................................................                              16,000
                             Total...................................................................................................................................................  $                 457,253,000
























                                                             408