Page 189 - 2022-23 Blue Book Vol 2
P. 189

Transportation

                                  Program Changes                           Direct Cost  Positions   Total Cost
           Changes in Salaries, Expense, Equipment, and Special

           Continuation of Services

             9. Metro Annual Work Program                                      5,529,702         -     8,195,330
                Continue funding and resolution authority for 52 positions
                consisting of two Accountants, one Senior Accountant I, one
                Transportation Planning Associate II, five Traffic Officer IIs,
                two Senior Traffic Supervisor Is, four Signal Systems
                Electricians, four Transportation Engineers, 15 Transportation
                Engineering Associate (TEA) IIs, 12 TEA IIIs, three TEA IVs,
                one Senior Management Analyst II, and two Management
                Analysts to support the Los Angeles Metropolitan
                Transportation Authority (Metro) Annual Work Program.
                Funding is provided by the Proposition C Anti-Gridlock Transit
                Improvement Fund ($1,538,146) and the Measure M Local
                Return Fund ($3,991,556) and the costs will be fully
                reimbursed by Metro. See related items in the Bureaus of
                Contract Administration, Engineering, Street Lighting, and
                Street Services. Related costs consist of employee benefits.
                SG: $5,529,702
                Related Costs: $2,665,628
            10. Complete Streets and Vision Zero Corridors                      635,704          -       942,463
                Continue funding and resolution authority for six positions
                consisting of four Transportation Engineering Associate IIs,
                one Transportation Engineering Associate III, and one Signal
                Systems Electrician to support the design, construction, and
                inspection of Complete Streets and Vision Zero corridor
                projects. Funding is provided by the Measure M Local Return
                Fund. See related Bureaus of Engineering, Street Lighting,
                and Street Services items. Related costs consist of employee
                benefits.
                SG: $635,704
                Related Costs: $306,759
           Restoration of Services
            11. Restoration of One-Time Expense Funding                         211,000          -       211,000
                Restore funding in the Paint and Sign Maintenance and
                Repairs Account that was reduced on a one-time basis in the
                2021-22 Budget.
                EX: $211,000


















                                                             729
   184   185   186   187   188   189   190   191   192   193   194