                                  Program Changes                           Direct Cost  Positions   Total Cost
           Changes in Salaries, Expense, Equipment, and Special

           New Services

            12. Metro Annual Work Plan - Transit Speed Improvements             385,147          -       590,442
                Add nine-months funding and resolution authority for five
                Project
                positions consisting of two Transportation Engineering
                Associate IIs, subject to pay grade determination by the Office
                of the City Administrative Officer (CAO), Employee Relations
                Division (ERD), one Transportation Engineering Associate II,
                subject to pay grade determination by the CAO ERD, one
                Transportation Engineering Associate II, and one
                Programmer/Analyst I, subject to pay grade determination by
                the CAO ERD, to support work related to the Transit Speed
                Improvement Project as part of the Los Angeles Metropolitan
                Transportation Authority (Metro) Annual Work Plan. Funding
                is provided by the Measure M Local Return Fund and the
                costs will be fully reimbursed by Metro. Related costs consist
                of employee benefits.
                SG: $385,147
                Related Costs: $205,295
            13. DWP Project Design and Construction Support                     688,958          -     1,042,745
                Add nine-months funding and resolution authority for eight
                positions consisting of one Senior Transportation Engineer,
                one Transportation Engineer, one Transportation Engineering
                Associate II, subject to pay grade determination by the Office
                of the City Administrative Officer, Employee Relations
                Division, three Transportation Engineering Associate IIs, one
                Signal Systems Electrician, and one Accountant to support
                the construction and design of Department of Water and
                Power (DWP) infrastructure improvement projects. All costs
                will be fully reimbursed by DWP. Related costs consist of
                employee benefits.

                SG: $688,958
                Related Costs: $353,787
           Efficiencies to Services

            14. Expense Account Reduction                                    (1,500,000)         -    (1,500,000)
                Reduce funding in the Contractual Services Account on a
                one-time basis to reflect anticipated expenditures, which
                include savings achieved due to Departmental efficiencies
                and expenditure reductions.
                EX: ($1,500,000)

            15. One-Time Salary Reduction                                    (1,300,000)         -    (1,752,529)
                Reduce funding in the Salaries General Account on a one-
                time basis to reflect savings generated by positions filled in-
                lieu, maintaining vacancies, and anticipated attrition. Related
                costs consist of employee benefits.
                SG: ($1,300,000)
                Related Costs: ($452,529)