Special Gas Tax Improvement Fund



                                                                                   2019-20             2020-21
                                                                               Adopted Budget     Proposed Budget

              DEPARTMENTAL APPROPRIATIONS

              Board of Public Works - Funds are provided for accounting support.   $          49,435   $        73,267




                                        Subtotal Departmental Appropriations     $        49,435   $         73,267



              SPECIAL PURPOSE FUND APPROPRIATIONS

              Asset Management and Inventory System - Funds were provided to             800,000                   -
              develop the Asset Management and Inventory system.

              Capital Improvement Expenditure Program* - Funds are provided           30,239,881         18,306,512
              for the design and construction of various street related projects,
              including flood control projects and safety-related lighting projects.

              Complete Streets -  Funds were provided for the reconstruction of        1,423,954                   -
              failed streets and Vision Zero safety improvements as part of the
              Complete Streets Program. This item was previously titled Street
              Reconstruction/Vision Zero Projects.

              Concrete Streets* -  Funds are provided for the reconstruction of         427,835           1,258,741
              concrete streets citywide.

              Cool Slurry - Funds are provided for the application of Cool Slurry              -          2,000,000
              treatments to prevent further deterioration of the roadway.

              Failed Street Reconstruction* -  Funds are provided for the              3,800,401          3,512,623
              reconstruction of failed pavement streets across the City.

              Pavement Preservation Program* -  Funds  are provided for                        -         23,996,188
              resurfacing, slurry sealing, and asphalt repairs to prevent further
              deterioration in the overall condition of the City street system.

              Sidewalk Repair Access Request Acceleration -  Funds were              10,000,000                    -
              provided  to accelerate sidewalk repair requests to safely separate
              vehicular and pedestrian traffic in compliance with the ADA.

              Sidewalk  Repair Contractual Services* - Funds are provided for          3,800,000          3,800,000
              sidewalk repair to safely separate vehicular and pedestrian traffic in
              compliance with the ADA.

              Sidewalk Engineering Consulting Services* - Funds are provided           2,700,000          2,300,000
              to pay for engineering consulting services for sidewalk repair work.

              Sidewalk Repair Incentive Program* - Funds are provided to allow               -            1,000,000
              the City to leverage sidewalk repair costs by sharing  costs with
              property owners. This helps to safely separate vehicular and
              pedestrian traffic in compliance with the ADA.