CTIEP - Summary

            The following table sets forth the proposed CTIEP for 2022-23 by project category, comparing the 2021-22 program
            to the 2022-23 program:


                        2022-23 CAPITAL AND TECHNOLOGY IMPROVEMENT EXPENDITURE PROGRAM

                                                                     2021-22                          2022-23
                                                                    Adopted           Change         Proposed
                                                                     Budget                           Budget


             Clean Water Projects                                 $   301,569,318   $    67,451,682  $   369,021,000

             Municipal Facilities Projects [3]


               Arts and Cultural Opportunities                    $          668,569   $       (338,082)  $          330,487
               Buildings and Facilities                               27,331,290           (354,833)   26,976,457
               Recreational Opportunities                                  3,100,000                         -           3,100,000

                                      Total – Municipal Facilities   $     31,099,859   $       (692,915)  $     30,406,944


             Physical Plant Projects [1,3]


               Watershed Management [4]                           $     23,617,414   $    (1,881,695)  $     21,735,719
               Street Repair and Pedestrian Improvement [4]             49,611,487        40,069,450        89,680,937
               Street Lighting [4]                                     9,780,000      (4,360,000)       5,420,000
               Contingencies [5]                                              500,000              500,000           1,000,000

                                          Total – Physical Plant   $     83,508,901  $     34,327,755  $   117,836,656

             Technology Projects

               Major Projects and System Replacements             $     25,989,470  $   (18,571,821)  $       7,417,649
               Citywide Infrastructure                                   27,383,036       (23,983,036)           3,400,000

                                             Total – Technology   $     53,372,506  $   (42,554,857)  $     10,817,649


                                                        TOTAL
                   CAPITAL AND TECHNOLOGY IMPROVEMENT
                                      EXPENDITURE PROGRAM         $   469,550,584  $     58,531,665  $   528,082,249

            [1]    The City Administrative Officer may approve changes in the planned use of funds between the General Fund, Special Gas Tax Street
                   Improvement Fund, SB1 Fund, Measure M Local Return Fund, Measure R Local Return Fund, Measure W Local Return Fund, and
                   Street Damage Restoration Fee Fund for approved Projects and may approve transfers of funds not required to complete approved
                   capital projects to other approved capital projects.

            [2]            MICLA and General Obligation Bond amounts are provided for informational purposes only.

            [3]            The City Administrative Officer may approve transfers within the same fund of $25,000 or 25 percent of project amounts (whichever
                   is greater), not to exceed $100,000, to or between eligible capital improvement projects or accounts approved by the Mayor and City
                   Council.

            [4]    Subject to receipt of actual funds from the Los Angeles Metropolitan Transportation Authority, County of Los Angles, and/or the State
                   of California.

            [5]            The City Administrative Officer may approve transfers of any amount from the Contingencies Account to any project listed or any
                   project previously approved by the Mayor and City Council.
                                                             900
   359   360   361   362   363   364   365   366   367   368   369