CAPITAL AND TECHNOLOGY IMPROVEMENT

                                        EXPENDITURE PROGRAM


                                        BASIS FOR THE PROPOSED BUDGET

                                                     CLEAN WATER


            The 2022-23 Proposed Budget for the Clean Water Capital and Technology Improvement Expenditure Program
            (CTIEP) relates to current year funding as follows:



                                                                      Amount                  %  Change
                 2021-22 Adopted Budget                                 301,569,318

                 2022-23 Proposed Budget                                369,021,000

                 Change from 2020-21 Budget                    $         67,451,682             22.4%


            The Clean Water CTIEP is administered by the Department of Public Works, Bureau of Sanitation and consists of
            wastewater facility improvement projects at the City’s four wastewater treatment plants and 49 pumping plants, as
            well as more than 6,700 miles of mainline sewers. The projects in the Clean Water CTIEP are divided into seven
            categories: Collection Systems, Donald C. Tillman Water Reclamation Plant, Hyperion Water Reclamation Plant,
            Los Angeles-Glendale Water Reclamation Plant, Pumping Plants, Terminal Island Water Reclamation Plant, and
            System-wide improvements.

            The Clean Water CTIEP is funded entirely from Clean Water System revenues, including the Sewer Service Charge
            (SSC).

            The current Clean Water CTIEP is focused on the ten-year Collection System Settlement Agreement (CSSA). The
            CSSA is a consent decree that articulates specific requirements for the wastewater collection system with the
            objective of reducing sewer spill risk and the associated overflow. While the ten-year term of the CSSA expired in
            2014, the Bureau of Sanitation plans to continue to meet and exceed the terms of the CSSA in order to avoid future
            liability and protect public health.


            BUDGET HIGHTLIGHTS:
              Funding in the amount of $94.8 million is provided for the construction of various collection system projects;

              Funding in the amount of $53.8 million is provided for the development of an Advanced Wastewater Purification
               Facility at the Donald C. Tillman Water Reclamation Plant in order to supply advanced treated recycled water
               to the Hansen Spreading Grounds; and,

              Funding in the amount of $21.2 million is provided for the development of an Advanced Wastewater Purification
               Facility at the Hyperion Water Reclamation Plant in order to supply advanced treated recycled water to the Los
               Angeles World Airports and nearby uses.