Page 380 - 2022-23 Blue Book Vol 2
P. 380
CTIEP – Municipal Facilities
MICLA-ISSUED FINANCING (cont.)
PROJECT TITLE CATEGORY* SEI* GI* ACTIVITY** 2022-23
AMOUNT
Pio Pico Library Pocket Park and Underground Parking 3,5 6 ✓ C $ 700,000
Funding is provided to construct pocket park features including a shade structure for children, perimeter fencing, and
library facade treatments.
Social Equity: This project is intended to address a lack of outdoor, recreational space for a high-density area that is
relatively park-deficient.
Public Safety Facilities - Animal Services 1,4 - - C $ 350,000
Funding is provided to support ongoing capital improvements at various Animal Services facilities.
Public Safety Facilities - Fire 1,4 - - C $ 500,000
Funding is provided to support ongoing capital improvements at various Fire Department facilities.
Public Safety Facilities - Police 1,4 - - C $ 700,000
Funding is provided to support ongoing capital improvements at various Police Department facilities.
Public Safety Facilities - Police Administration Building 1,4 5 - C $ 280,000
Funding is provided to support ongoing capital improvements at the Public Administration Building.
Reseda Roller Skating Rink and Ice Skating Facility 1,2,5 6 - C $ 1,500,000
Funding is provided to offset a funding shortfall and to proceed with construction of an indoor ice skating and
rollerblade rink facility as part of a Proposition K Specified project that leverages multiple funding sources.
Social Equity: This project would serve as a regional facility, to expand public access to ice skating and skating rink
facilities.
Reseda Theatre Roof Rehabilitation 1 7 - C $ 450,000
Funding is provided to repair the roof of the Reseda Theatre.
Serrania Park Restroom 1,2 8 - C $ 862,101
Funding is provided to address the remaining shortfall for this project. The project scope is for new restroom
construction.
Sheldon Arleta Phase III C - Baseball Field and Picnic Area 3,5 6 ✓ D,C $ 700,000
Funding is provided to address the remaining shortfall of a multi-phased project to convert closed landfill into a
40-acre regional park.
Social Equity: This project will serve as a regional facility that will increase recreational space and youth programming.
Sixth Street Viaduct Replacement Project - Continued 1,2 7 - C $ 800,000
Construction Funding
Funding is provided for the Sixth Street Viaduct Replacement Project right-of-way time related impacts and other
construction support costs.
916