CATEGORY* PROJECT TITLE ACTIVITY** 2020-21 AMOUNT
M Oakdell Road (3180) Bulkhead C $ 545,000
Funding is provided by the SB1 Fund to construct a new concrete bulkhead to restore lateral support and safety to the
roadway and to avoid a collapse of the public right of way onto a private residential property.
M Olympic Blvd and Mateo Street Phase C $ 1,171,452
II Street Improvements
Funding is provided by the SB1 Fund to supplement an existing grant funded project to widen an intersection and
install curb ramps, traffic signals, street lighting, and striping. This improves traffic flow and increases safety.
M Pacific View Trail (2849) Retaining Wall C $ 749,000
Replacement
Funding is provided by the SB1 Fund to remove and replace a failing timber retaining wall with a new steel beam and
concrete lagging debris structure to provide safe passage for pedestrians and vehicles.
M Safe Routes to School Street Safety C $ 370,000
Improvements Phase I
Funding is provided by the SB1 Fund to complete design and implementation of Safe Routes to School Phase I
engineering treatments to improve safe passage for pedestrians and vehicles.
M Safety Related Drainage Projects C $ 646,000
Funding is provided by the SB1 Fund to correct drainage problems in City streets primarily caused by aged and worn
gutters, cross-gutters, and curbs.
M Sepulveda Blvd (LAX) Tunnel Fire Detection C $ 303,000
System Upgrade
Funding is provided by the SB1 Fund to upgrade the Fire Detection System in the Sepulveda Tunnel to maximize
public safety.
M Sepulveda Blvd (LAX) Tunnel Cleaning and C $ 245,494
Safety Maintenance
Funding is provided by the SB1 Fund to maintain various safety mechanisms within the tunnel.
M Sherman Way Tunnel Safety Maintenance C $ 105,887
Funding is provided by the SB1 Fund to maintain various safety mechanisms within the tunnel.
M Sunset Blvd at Allenford Ave Slope Mitigation C $ 164,000
Funding is provided by the SB1 Fund to install K-rail to protect the roadway and stormdrain from slough, sediment, and
debris that causes flooding and to provide safe passage for vehicular traffic.
* "FC" indicates Flood Control; "SL" indicates Street Lighting; "M" indicates Miscellaneous (e.g. soundwalls & bulkheads); "WQ" indicates Water Quality.
** “PP” indicates preliminary study. “D” indicates design. “C” indicates construction work. “R/W” indicates land or building acquisition.
861