Page 396 - 2022-23 Blue Book Vol 2
P. 396

CTIEP – Physical Plant

            STREETS PROJECTS (cont.)

            PROJECT TITLE
                                                                  CATEGORY*  SEI*  GI*  ACTIVITY**    2022-23
                                                                                                      AMOUNT
            Paseo Miramar (767)
                                                                       1,4       9    -      C      $       291,000

            Funding is provided by the Street Damage Restoration Fee Fund to reconstruct roadway, curb and gutter, and
            sidewalk to ensure public safety.

            Plummer/Natick Crosswalk                                    1        7    -      C      $       250,000

            Funding is provided by the Measure M Local Return Fund to install a crosswalk at the intersection of Plummer and
            Natick.

            Quail Drive (680) Retaining Wall Replacement               1,4       8    -      C      $       443,000

            Funding is provided by the SB1 Fund to install a new steel pile and concrete lagging bulkhead to replace an existing
            failing concrete retaining wall to restore lateral support to the roadway and ensure public safety.

            Radford Ave. over LA River Bridge Repairs                  1,4       8    -      C      $       250,000

            Funding is provided by the Special Gas Tax Street Improvement Fund to reconstruct the access ramps, concrete
            sidewalks, railing, and curb and gutter.

            Rail to Rail (R2R) Project                                1,3,5      4          C      $    9,000,000

            Funding is provided by the SB1 Fund ($3,724,000) and Measure M Local Return Fund ($5,276,000) to partially fund
            the project cost that is within the City’s right-of-way. The project, which will be implemented by Metro, will convert the
            underutilized railroad right-of-way into a multi-purpose transportation corridor, creating a new east-west pedestrian and
            bicycle corridor, connections to numerous transit lines, and enhancing the existing and future bicycle network.


            Reimagine Venture Blvd. – Phase 2                           1        8    -      D      $       400,000
            Funding is provided by the Measure M Local Return Fund for street improvement work along Ventura Blvd.

            Rockledge Road (2120) Retaining Wall Replacement           1,4       7    -      C      $       330,000

            Funding is provided by the SB1 Fund to install a new steel beam and pre-cast concrete lagging bulkhead to restore
            lateral support to the existing roadway and ensure public safety.
            Safety Railing near 1780 Rotary Drive                       1        7    -      C      $         75,000

            Funding is provided to install a handrail onto the curbing wall along the existing stairs. The handrail will provide
            additional safety for users of this public facility.

            Safety Related Drainage Projects                           1,4       -    -      C      $       500,000

            Funding is provided for slope erosion repair, street reconstruction, installation of asphalt concrete (AC) berm or
            concrete curb, AC pavement, and any street remedial work to address localized needs that are below the thresholds of
            capital repair projects.






            * "1" Health & Safety, “2” Legal Mandate, “3” Resiliency and Sustainability, “4” Operations and Cost Savings, “5” Equitable Community and Economic
            Sustainability/Social Equity. “SEI” Social Equity Index (See CTIEP Summary for SEI definition). “GI” Green Investment.
            ** “PP” preliminary study. “D” design. “C” construction work. “R/W” land or building acquisition. “PC” post-construction.
                                                             932